Southerly Waste Water Treatement Plant
City of Columbus
New Raw Sewage Pump and Grit & Screen Buildings
Overhead Primary Power Modification and Upgrade
- Installed new 14,400 volt primary overhead service for extension of existing primary north loop. (Approximately 700 feet of 1351 MCM 3 phase line)
- Terminated cables with dead end insulators.
- Tied in 1000 MCM at riser poles with 12 heat shrink terminations.
- Installed new poles and built new 3 phase line.
- Installed new group operated air brake switch.