Claypool Electric
  

Edgetech

Location:  Cambridge, OH

Project Owner:

Quanex Building Products

2012

 

Claypool Electric was hired by Edgetech to act as the electrical
contractor on the renovation and expansion of there facility in
Cambridge, OH.  The project took roughly five months, and was
complicated when a natural disaster hit the facility from which
they were moving equipment to be installed during this renovation. 
At that point, we had to respond to the needs of the client and finish
a month of work in two weeks.

We were able to respond with increased manpower over two shifts
working seven days a week to finish the project.  At one point we
had over 40 electricians working in their facility, demonstrating our
ability to leverage our considerable manpower resources to get the job completed.

Work completed included moving 12 extruder lines, 6 ovens and two
mixing systems.  The installation of 9 new 600 Amp bussways ranging
from 60 to 150 linear feet.  To power the new equipment, a new unit substation was installed with 480 volt switchgear and a new 15 KV
feed.  Each bussway was fed with parallel feeds of 750 MCM aluminum
in a 36” cable tray system of over 10,000 feet.  Finally, a new chiller
system was installed for the facility for which we completed all power
and control wiring.

 
  